During February we continue to see changes to both the interior and exterior of the Old Cathedral. The Restoration Project is on target to complete later in 2014. Before that mystery day, there is still a great deal of work to be done.

The pews have already been removed and are in the process of being refinished offsite. The following interior work is already underway and continues through these next few months:

  • The repairing and refinishing of the plaster,
  • The refurbishing of panels, doors and trim,
  • Replacement and enhancement of all the lighting fixtures,
  • Continued work on the new heating and cooling system, and
  • The removal and restoration of the Cross and Orb from high atop the Church steeple.

Thank you for your continued support and generosity. We will continue to keep you informed as other scheduled work begins.